Filing deadlines · computed November 27, 2026

SEC filing deadlines for a February 28 fiscal year end

For a fiscal year ending February 28, 2027, the 10-K is due Thursday, April 29, 2027 for a large accelerated filer, Friday, May 14, 2027 for an accelerated filer and Tuesday, June 1, 2027 for a non-accelerated filer (day 90 is Saturday, May 29, 2027, so Rule 0-3 moves it). A definitive proxy statement that supplies Part III must be filed by Monday, June 28, 2027.

3 roster companies close their fiscal year on February 28, and 1 closes a 52- or 53-week year within a week of it, per EDGAR submissions data read November 12, 2026.

Fiscal year ending February 28, 2027

A day under a due day is where the count landed before Rule 0-3 moved it.

Rule 0-3 moves 3 due days off a weekend or holiday in this cycle: the Q2 10-Q (large accelerated and accelerated) from October 10, 2026 to October 13, 2026; the Q3 10-Q (large accelerated and accelerated) from January 9, 2027 to January 11, 2027; and the 10-K (non-accelerated) from May 29, 2027 to June 1, 2027.

Filing days for the fiscal year ending February 28, 2027. 1. Q1 10-Q, day 40: July 10, 2026; 2. Q1 10-Q, day 45: July 15, 2026; 3. Q2 10-Q, day 40: October 13, 2026; 4. Q2 10-Q, day 45: October 15, 2026; 5. Q3 10-Q, day 40: January 11, 2027; 6. Q3 10-Q, day 45: January 14, 2027; 7. Fiscal year end: February 28, 2027; 8. 10-K, day 60: April 29, 2027; 9. 10-K, day 75: May 14, 2027; 10. 10-K, day 90: June 1, 2027; 11. Proxy for Part III, day 120: June 28, 2027JunJulAugSepOctNovDecJanFebMarAprMayJun1234567891011
The fiscal year ending February 28, 2027: three 10-Qs inside it, then the 10-K 60, 75, 90 days after it by filer category and the Part III proxy by day 120 (shaded). Days computed from the forms' General Instructions and Rule 0-3; numbers match the list below.
  1. 1Q1 10-Q, day 40 (large accelerated and accelerated)Fri, July 10, 2026
  2. 2Q1 10-Q, day 45 (non-accelerated)Wed, July 15, 2026
  3. 3Q2 10-Q, day 40 (large accelerated and accelerated)Tue, October 13, 2026
  4. 4Q2 10-Q, day 45 (non-accelerated)Thu, October 15, 2026
  5. 5Q3 10-Q, day 40 (large accelerated and accelerated)Mon, January 11, 2027
  6. 6Q3 10-Q, day 45 (non-accelerated)Thu, January 14, 2027
  7. 7Fiscal year endSun, February 28, 2027
  8. 810-K, day 60 (large accelerated)Thu, April 29, 2027
  9. 910-K, day 75 (accelerated)Fri, May 14, 2027
  10. 1010-K, day 90 (non-accelerated)Tue, June 1, 2027
  11. 11Proxy for Part III, day 120Mon, June 28, 2027
Due days for the fiscal year ending February 28, 2027, by filer category.
FilingPeriod endDays afterLarge acceleratedAcceleratedNon-accelerated
Q1 10-QMay 31, 202640 / 40 / 45Fri, July 10, 2026Fri, July 10, 2026Wed, July 15, 2026
Q2 10-QAugust 31, 202640 / 40 / 45Tue, October 13, 2026from Saturday October 10Tue, October 13, 2026from Saturday October 10Thu, October 15, 2026
Q3 10-QNovember 30, 202640 / 40 / 45Mon, January 11, 2027from Saturday January 9Mon, January 11, 2027from Saturday January 9Thu, January 14, 2027
10-KFebruary 28, 202760 / 75 / 90Thu, April 29, 2027Fri, May 14, 2027Tue, June 1, 2027from Saturday May 29
Proxy for Part IIIFebruary 28, 2027120Mon, June 28, 2027Mon, June 28, 2027Mon, June 28, 2027

Fiscal year ending February 29, 2028

For a fiscal year ending February 29, 2028, the 10-K is due Monday, May 1, 2028 for a large accelerated filer (day 60 is Saturday, April 29, 2028, so Rule 0-3 moves it), Monday, May 15, 2028 for an accelerated filer (day 75 is Sunday, May 14, 2028, so Rule 0-3 moves it) and Tuesday, May 30, 2028 for a non-accelerated filer (day 90 is Monday, May 29, 2028, so Rule 0-3 moves it). A definitive proxy statement that supplies Part III must be filed by Wednesday, June 28, 2028.

Rule 0-3 moves 6 due days off a weekend or holiday in this cycle: the Q1 10-Q (large accelerated and accelerated) from July 10, 2027 to July 12, 2027; the Q2 10-Q (large accelerated and accelerated) from October 10, 2027 to October 12, 2027; the Q3 10-Q (large accelerated and accelerated) from January 9, 2028 to January 10, 2028; the 10-K (large accelerated) from April 29, 2028 to May 1, 2028; the 10-K (accelerated) from May 14, 2028 to May 15, 2028; and the 10-K (non-accelerated) from May 29, 2028 to May 30, 2028.

Filing days for the fiscal year ending February 29, 2028. 1. Q1 10-Q, day 40: July 12, 2027; 2. Q1 10-Q, day 45: July 15, 2027; 3. Q2 10-Q, day 40: October 12, 2027; 4. Q2 10-Q, day 45: October 15, 2027; 5. Q3 10-Q, day 40: January 10, 2028; 6. Q3 10-Q, day 45: January 14, 2028; 7. Fiscal year end: February 29, 2028; 8. 10-K, day 60: May 1, 2028; 9. 10-K, day 75: May 15, 2028; 10. 10-K, day 90: May 30, 2028; 11. Proxy for Part III, day 120: June 28, 2028JunJulAugSepOctNovDecJanFebMarAprMayJun1234567891011
The fiscal year ending February 29, 2028: three 10-Qs inside it, then the 10-K 60, 75, 90 days after it by filer category and the Part III proxy by day 120 (shaded). Numbers match the list below.
  1. 1Q1 10-Q, day 40 (large accelerated and accelerated)Mon, July 12, 2027
  2. 2Q1 10-Q, day 45 (non-accelerated)Thu, July 15, 2027
  3. 3Q2 10-Q, day 40 (large accelerated and accelerated)Tue, October 12, 2027
  4. 4Q2 10-Q, day 45 (non-accelerated)Fri, October 15, 2027
  5. 5Q3 10-Q, day 40 (large accelerated and accelerated)Mon, January 10, 2028
  6. 6Q3 10-Q, day 45 (non-accelerated)Fri, January 14, 2028
  7. 7Fiscal year endTue, February 29, 2028
  8. 810-K, day 60 (large accelerated)Mon, May 1, 2028
  9. 910-K, day 75 (accelerated)Mon, May 15, 2028
  10. 1010-K, day 90 (non-accelerated)Tue, May 30, 2028
  11. 11Proxy for Part III, day 120Wed, June 28, 2028
Due days for the fiscal year ending February 29, 2028, by filer category.
FilingPeriod endDays afterLarge acceleratedAcceleratedNon-accelerated
Q1 10-QMay 31, 202740 / 40 / 45Mon, July 12, 2027from Saturday July 10Mon, July 12, 2027from Saturday July 10Thu, July 15, 2027
Q2 10-QAugust 31, 202740 / 40 / 45Tue, October 12, 2027from Sunday October 10Tue, October 12, 2027from Sunday October 10Fri, October 15, 2027
Q3 10-QNovember 30, 202740 / 40 / 45Mon, January 10, 2028from Sunday January 9Mon, January 10, 2028from Sunday January 9Fri, January 14, 2028
10-KFebruary 29, 202860 / 75 / 90Mon, May 1, 2028from Saturday April 29Mon, May 15, 2028from Sunday May 14Tue, May 30, 2028from Monday May 29
Proxy for Part IIIFebruary 29, 2028120Wed, June 28, 2028Wed, June 28, 2028Wed, June 28, 2028

Other fiscal year ends

January 31 · March 31 · April 30 · May 31 · June 30 · July 31 · August 31 · September 30 · October 31 · November 30 · December 31

Any other day, and the Form 8-K count: the calculator.

Sources